Temporary Access Road for Padel Court Construction, Coventry

24 November 2026 ยท Coventry

Sports & Leisure

Notus Ground Safe installed a 100 m bolted trackway access road in a single day, giving dumper trucks a safe route to a padel court build in Coventry while protecting the grass beneath.

Completed temporary access road between court fencing and tree line at Cryfield Sports Pavilion, Coventry
Cryfield Sports PavilionCoventry (CV4 7AL)
Fosse Contracts LtdMain contractor
100 mBolted trackway access road (c. 300 mยฒ)
40Heavy-duty panels (3 m ร— 2.5 m)
1 dayInstallation, 24 November 2026
24 Nov โ€“ 22 Dec 2026Hire period (road on site)

Introduction

Replacing existing netball courts with new padel courts at Cryfield Sports Pavilion called for a dependable temporary route for dumper trucks โ€” without damaging the narrow grass corridor between court fencing and mature trees. Fosse Contracts Ltd asked Notus Ground Safe to supply, install and later recover a bolted trackway road along that line.

The challenge

The only route in for plant was a narrow strip of grass between the existing court fencing and a line of mature trees. Fosse Contracts needed dumper trucks running along it every day to remove the old court surfacing and bring in materials for the new padel courts.

  • Tight corridor: high court fencing on one side and temporary Heras fencing against the tree line on the other left little room to manoeuvre.
  • Soft ground in late autumn: repeated dumper passes in wet November weather would quickly rut the grass and could leave the route impassable.
  • Finished surfaces nearby: the route ran right alongside a newly surfaced court, so mud and damage had to be kept off it.
  • Reinstatement risk: any damage to the grass would mean extra cost and time for the client at the end of the job.

Our solution

We laid a continuous, bolted trackway road along the full length of the corridor, installed and recovered by our own crew.

  • Planning: site-specific RAMS were issued to the main contractor before work started, and the hire contract set out the panel count and route.
  • Delivery and placement: a telehandler lifted each 3 m ร— 2.5 m heavy-duty panel off the load and placed it nose to tail along the route, working forward over the panels already laid.
  • Bolted joints: our crew bolted every joint by hand so the panels act as one road and stay locked in place under repeated dumper traffic.
  • Transitions: Euro mats and PVC rubber matting were used at the ends and edges to give a smooth step on and off the road and protect the surrounding surfaces.
  • Ongoing support and recovery: the road stays in place for the duration of the works (24 November to 22 December 2026), and when the courts are complete we will lift every panel and leave the ground as we found it.

The road was laid in a single day, so the contractor could start running dumpers along it straight away.

The result

Fosse Contracts got a firm, all-weather route for its dumper trucks from day one, with the grass and nearby courts protected throughout.

  • Work keeps moving: dumpers run along a solid surface whatever the weather, so rain does not stop deliveries or muck-away.
  • Safer site: a defined, level route inside fenced edges keeps plant movements predictable for operatives and pedestrians.
  • Ground protected: the panels spread the load and keep tyres off the turf, avoiding ruts and mud.
  • No reinstatement bill: once the panels are lifted, the client should not face costly turf repairs.
  • One supplier, start to finish: Notus handled planning, RAMS, delivery, installation and recovery with our own crew and plant.

Project photos

The finished road runs the full length of the corridor between the court fencing and the tree line.

Project video

Video thumbnail: temporary access road for padel court construction, Coventry

Need temporary access on your next project?

Whether it's a sports facility, a rail possession, a cable route or a ground investigation, Notus Ground Safe can design, supply, install and recover the right temporary access for your site. We're RISQS verified and work nationwide.

Contact Us โ†’